Demolition of the existing forecourt, lanes and retail structure and construction of a new full-service facility with shopfront, retail centre, forecourt and canopy. Concrete tilt-panel construction with a new solid canopy over 12 lanes. 

Challenge

Complete construction within the 12-week timeframe on a tight site located on a busy section of State Highway 1. The project required us to relocate multiple underground storage tanks & bowsers and contain, capture and treat all run-off. Team Trigg managed unavoidable delays to finish ahead of schedule and complete all work to Chevron NZ Ltd safety procedures and regulations. 

Outcome

A state-of-the-art modern, full-service petrol station with easy access from the main arterial route. Open for business one week ahead of schedule, with all regulatory conditions met or exceeded and all environmental concerns managed professionally, to international standards. We’re very proud of this retail construction project, and our clients were also thrilled with both the process and the time and financial outcomes.

More To Explore

Eye Specialists

A multi-award-winning building with a specialist eye clinic and state-of-the-art surgery facilities.

Thanks for downloading our FREE guide

Check your email inbox – it’s on its way!